Pengerjaan Konstruksi MRT Bundaran Senayan-HI Capai 70 Persen

Bundaran Senayan-HI MRT Construction Reaches 70 Percent

The construction of Mass Rapid Transit (MRT) from Bundaran Senayan-Bundaran HI has reached 70 percent. Underground drilling has reached 1.4 kilometer.

The platform (peron) has reached 50 percent. Totally, the project reaches 70 percent

“The platform (peron) has reached 50 percent. Totally, the project reaches 70 percent. This is not included the signal and installation project,” said Mohammad Natsir, Operation and Maintenance Director of Jakarta MRT, Thursday (9/8).

Meanwhile, drilling process has reached 1.4 kilometer from Bundaran Senayan to Semanggi and Bundaran HI to Dukuh Atas Station.

MRT Flyover Lane Enters Girder Installation

“Bundaran HI station will be integrated with Transjakarta,” he added.

Related with land buying process, South Jakarta Mayor, Tri Kurniadi admitted his side keeps pursuing the target. There are 38 land lots in Cipete being processed. The land is handled by Jakarta Dept. of Bina Marga and Dept. of Transportation.

“Payment target is completed in December 2016. We offer Rp 26 million per meter square, but the owners ask Rp 150 million,” he admitted.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye804 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye707 personDessy Suciati
  3. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye678 personNurito
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye646 personTiyo Surya Sakti
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye452 personDessy Suciati